Offshore/Onshore Operating Requirements

Offshore Pipelines Activities

Environment Plan (EP)

An EP is required for the construction and operation, including hydrotesting of all pipelines conveying petroleum in Commonwealth and State waters. The following document Guidelines for the Preparation and Submission of an Environment Plan provides guidance for companies on the EP regime and content.

Pipeline Management Plan

A Pipeline Management Plan is required for the construction and operation of all pipelines conveying petroleum in Commonwealth and State waters. This is administered by the National Offshore Petroleum Safety Authority for Commonwealth waters. Refer to their website www.nopsa.gov.au for further information.

Submission requirements

The EP must be submitted as early as possible, but at least 30 days before commencement of activities, to allow sufficient time for regulators to assess and resubmission of inadequate documents. The document must be submitted electronically and in hard copy to:

Aaron DeFina
General Manager, Technical Services
GPO Box 4440 Melbourne 3001
aaron.defina@dsdbi.vic.gov.au

Other statutory requirements

Consent to construct The written consent of the Minister is required before commencement of pipeline operation.
Consent to operate

The written consent of the Minister is required before commencement of pipeline operation

Summary EP's The operator must submit a summary EP for public disclosure within 10 days of acceptance of the EP in accordance with Regulation 11 of the Petroleum (Submerged Lands) (Management of Environment) Regulations 1999.
Notification of incidents All incidents must be notified to the Department in accordance with the relevant Regulations, on a dedicated incident mobile number 0419 597 010.

 

List of the current summary Environment Plans.

Useful websites

Australian Fisheries Management Authority

for information about the management of Commonwealth fisheries

Australian Maritime Safety Authority

for information about marine safety in Commonwealth water

Department of Environment, Water, Heritage and Arts

for information about the requirements of the Environment Protection Biodiversity Conservation Act 1999 and Environment Protection (Sea Dumping) Act 1981

Department of Environment and Primary Industries – Fisheries

for information about the management of State fisheries

Marine Safety Victoria

for information about marine safety in State waters

National Offshore Petroleum Safety Authority

for information about occupational health and safety for the petroleum industry in Commonwealth and State waters

Department of Resources, Energy and Tourism

for further information on upstream petroleum in Commonwealth waters

Onshore Pipelines Activities

Consultation Plan (CP)

An approved CP is required prior to a proponent giving notice to each land owner and occupier of intention to enter land or of a pipeline corridor.

Construction Environmental Management Plan (CEMP)

A CEMP is required prior to construction of all pipelines. The Pipeline Regulations 2007 sets out the matters to be included in a CEMP. Further information can also be sought by contacting Departmental officers.

Construction Safety Management Plan (CSMP)

A CSMP is required prior to construction of any pipeline. This is administered by Energy Safety Victoria (ESV). The requirement for an Operational Environmental Management Plan and Operational Safety Management Plan is also administered by ESV.

Submission requirements

All statutory documents must be submitted as early as possible, but at least 30 days before commencement of activities, to allow sufficient time for regulators to assess and resubmission of inadequate documents. The documents must be submitted electronically and in hard copy to:

Earth Resources Information Centre

Postal address:
Department of State Development, Business and Innovation
Earth Resources Information Centre
GPO Box 4509
Melbourne VIC 3001

Other statutory requirements

Planning permit exemption Section 85 of the Pipelines Act 2005 states a licence issued under this Act negates the requirement to obtain a planning permit under the Planning and Environment Act 1987.
Rehabilitation bond A rehabilitation bond, in the form of a bank guarantee and in an amount determined by the Department is required.
Notification of incidents All incidents must be notified to the Department in accordance with the relevant Regulations, on a dedicated incident mobile number 0419 597 010.
Consent to operate The written consent of the Minister is required before commencement of pipeline operation.
OEMP Operational Environment Management Plan is required prior to the consent to operate. This is assessed by ESV.
OSMP Operational Safety Management Plan is required prior to the consent to operate. This is assessed by ESV.

Useful websites

Australian Pipeline Industry Association

for information about advice on management of pipeline issues including their Code of Environmental Practice

Department of Environment, Water, Heritage and Arts

for information about the requirements of the Environment Protection Biodiversity Conservation Act 1999 and Environment Protection (Sea Dumping) Act 1981

Environment Protection Authority

for information about the application of the Environment Protection Act 1970

Department of Environment and Primary Industries

for information about biodiversity and conservation issues